Business today needs to be efficient in all aspects of its operation and the reliability of a computer facility is no different. A computer room requires the coming together of many facets of design to create an effective and efficient end result.

Design considerations include architectural requirements, equipment layout, cable management, electrical power supply, backup, fire, safety, security and mechanical services.

Hirotec Technologies has over 20 years experience in the design of mechanical services in computer and IT facilities. As such, we are able to provide valuable information about equipment selection and application with the best solution for a particular facility.

Air conditioning equipment selection is critical to the success of overall room operation in particular the ability to maintain required environment conditioning within the facility.

Incorrect selection of equipment type can make the installation process both difficult and costly, whilst incorrect selection of number and capacity of units will most certainly impact on room conditions achievable throughout the year.

10 Point Equipment Selection Checklist (room design and application)

  1. Determine proposed room size and shape plus raised floor and ceiling heights.
  2. Determine electronic equipment layout and individual heat loads.
  3. Determine future electronic equipment expansion plans.
  4. Determine air intake locations and volume for each piece of equipment.
  5. Determine proposed layouts and size of cable trays and pipes within the facility.
  6. Determine room design temperature, humidity and allowable gradients.
  7. Determine external heat considerations to the room.
  8. Determine the vapour barrier treatment to the room components.
  9. Determine possible locations for air conditioning equipment both inside and outside the room plus access for piping and wiring.
  10. Determine required interfaces to BMCS’ Vesda or other systems.

The above check list provides a basis for initial selection of system type, capacity, and number of units required to appropriately condition a particular facility whilst retaining a high level of reliability in underlying room design.

If you have an existing computer facility and would like to know how well it serves your businesses current or future requirements, download Hirotec’s Room Design Checklist or talk to one of our experts at our Sydney, Melbourne or Canberra offices.

Room Design Checklist (PDF 149kb)

 

air conditioned computer room

  ©Copyright 2002-2003 Hirotec International Pty Ltd
employment | contact | usage policy | privacy